Page 32 - Burstlining
P. 32

LUDWIG PFEIFFER
















                                         Reference project for Grundoburst 2500G





         Scope of work:                             Rehabilitation of a drinking water pipeline DN

                                                    800 with a length of 130 m


         Old pipe:                                  Ductile iron DN 800


         New pipe:                                  Steel DN 800, with a protection layer of

                                                    concrete



         Machine:                                   GRUNDOBURST 2500 G


         Performance time:                          3 working days for pushing the rods, the

                                                    welding of the pipes and the pulling-in process